Rediscovering the Obvious

…stumbling in the footsteps of greatness

The SAFe program portfolio: A lean perspective on limits

without comments

There’s a discussion over at kanbandev about the feasibility of how SAFe’s WIP limiting approaches work at the portfolio level, and I wrote up a few thoughts… cross-posted here for longer term availability.

There are few nuances that are important to understand when discussing how the portfolio level in SAFe is limited, and I apologize in advance if the following comes off as a lecture. The details are hard to assemble from the web site, but are somewhat more clear in the portfolio module of the course materials.

Epic Analysis flow: The only explicit, count-based limit in the portfolio kanban in SAFe is limiting the number of epics permitted to be in analysis and pre-approval at any given time. SAFe recommends the WIP constraint here is determined based on the desired epic throughput (pull rate from portfolio backlog into implementing) and the availability of the architectural and development capacity to perform analysis. In the past this was framed as “limited by the number of epic owners”, but this didn’t properly represent the bottleneck. Reference

Portfolio backlog: While there is no explicit limit set to the portfolio backlog size, in practice it has an implicit limit based on desired aging and investment flow characteristics. If items in the portfolio are consistently being passed in the final cost of delay sequencing, they are candidates to be pulled out and eliminated or passed back through the analysis flow for reconsideration and rescoping.

Implementation: There is an explicit, flow-based capacity limit between the portfolio backlog active implementation by the various trains. The limit is managed as an explicit pull system where the trains may pull in the work at the cadenced PI boundaries if they have capacity to support it. Forecasting and capacity recognition is done in “big round number” story points, generally derived from reference class forecasting or relative estimation approaches performed against a preliminary feature decomposition. Reference. Capacity may be reserved by allocating budget against the epics, representing an explicit, cross-cutting investment decision by the executives forming the program portfolio management team. Reference

Portfolio Distribution: SAFe significantly simplifies the decisionmaking around the above concerns through the recommended budgeting approach, which explicit allocates both budget, delegated financial authority, and scope determination to the release trains as the default approach. This leads to a significantly reduced portion of the overall spend being managed as explicit items in the portfolio flow, Instead, the majority of the work can flow “horizontally” at the train level without incurring the administrative and governance overhead associated with the larger items flowing through the portfolio backlog. The portfolio flow is intended to be used only for those items that cut across trains and are of sufficient size that they need explicit financial governance. Reference. SAFe additionally provides an optional value-stream level coordination layer to manage coordination of those cross-cutting items that demand additional coordination due to the various dependencies that remain after making the organizational structure trade-off decisions without adding the additional financial governance overhead. Reference.

In my experience working with organizations consulting and training SAFe, this final aspect is the hardest part to adopt organizationally, as it incurs the same set of challenges that evolving towards a incremental funding / Beyond Budgeting approach does. As a result, these organizations tend to flow a much higher percentage of their work through the portfolio than should be necessary and incur the significantly longer lead times associated with doing so. They also tend to enter a negatively reinforcing loop of excessive cross-train dependencies and failure to achieve multi-train continuous improvement. I know a few companies that have navigated their way through this trap, but it is one of the bigger SAFe anti-patterns I’ve observed, at least early in adoption efforts.

Written by erwilleke

October 16th, 2014 at 2:39 pm

Posted in Uncategorized